A NUMBER of town centre roads are set for resurfacing.

It will take place as follows:

Eastgate, from February 3 for approximately six weeks. Diversion route: Church Street/Regent Street, one way restriction revoked.

Market Hill from February 18 for approximately six weeks. Diversion route: Old Mill Lane/Church Street/Shambles Street.

Royal Street, from March 8 for approximately three weeks. One way restriction will be revoked.

Eldon Street, from March 9 for approximately two weeks. Diversion route: Old Mill Lane/Church Street/Shambles Street.

Regent Street, from March 24 for approximately one week. Diversion route: Church Street/Shambles Street/St Mary's Place/Church Lane/Old Mill Lane/Harborough Hill Road/Eldon Street North.

Work has been taking place since the end of June 2014, with Eldon Street, Regent Street South, Hanson Street, Royal Street, Regent Street, Eastgate, Market Hill and Church Street's footpath undergoing improvements.

Pedestrian access to properties and businesses adjacent to the works will be maintained throughout the duration, although vehicular access may be restricted at times as work is carried out across business frontages.